22 | 4TH - 10TH MAY 2018 | UTILITY WEEK Operations & Assets High viz The first offshore substation topside was successfully installed last week at Orsted's Hornsea Project One wind farm, 120km off the Yorkshire coast. Weighing 2,800 tonnes, the sub station, Z12, was installed on its sup port by Semco Maritime's crane vessel Saipem 7000. The Z12 offshore substation is one of three that will collect electricity from the windfarm's 174 turbines and transform it to a higher voltage so it can be exported to shore with fewer losses. As a result of the unprecedented cable lengths, being located so far off Substation success