Utility Week

UTILITY Week 17th November 2017

Utility Week - authoritative, impartial and essential reading for senior people within utilities, regulators and government

Issue link: https://fhpublishing.uberflip.com/i/901108

Contents of this Issue

Navigation

Page 21 of 31

22 | 17TH - 23RD NOVEMBER 2017 | UTILITY WEEK Operations & Assets Market view H ugely expensive and with a multi- tude of moving parts, it's a very long shot to expect any large build-based energy project to be delivered completely on time and to plan. There's an element of risk in almost every energy project – and you need only to picture this fairly usual situa- tion to understand how. A contractor is asked to tender for a pro- ject that contains a series of stringent require- ments, with the customer even specifying the exact design they want to be delivered. The contractor builds to the customer's design, knowing that – inevitably – it contains some imperfections, but assuming that the cus- tomer will be understanding of this and allow some flex around the requirements. Fast for- ward six months, a year or maybe even longer – and the customer lodges a complaint that not all of their requirements have been met. A recent ruling concerning an offshore windfarm by the UK's Supreme Court has highlighted just how much contractors carry this risk in energy projects. MT Hojgaard vs Eon Climate and Renewables In the case of MT Hojgaard versus Eon Cli- mate and Renewables, the contractor, MT Hojgaard, agreed to deliver the turbines for the Robin Rigg windfarm to specified crite- ria, which included conformity with an inter- national design standard for offshore wind turbines known as J101. The contractor also agreed to design the turbine foundations so that they would have a lifetime of 20 years without planned replacement. J101 provided a mathematical formula to calculate aspects of the foundation structure, but this unfor- tunately contained an error – meaning that the foundations built were about ten times weaker than required. Corrective works commenced immedi- ately when it became apparent that the foun- dations were failing. And so the question arose, who was liable to foot the £26 million cost of the remediation? The court found that the contractor was liable for the failure to provide a design that was capable of ensuring the turbines would have a lifetime of 20 years without planned replacement. It was no excuse that the design had been prepared on the basis of international standard J101, even though the customer had required conformity with J101. In other words, the contractor was liable for an error in the international standard that rendered the turbine design unable to meet other contractually agreed criteria. The case sets a precedent that total responsibility lies with the contractor to ensure that the item produced complies with the prescribed criteria, even if the cus- tomer specified the design. Is it any differ- ent if the customer "assured" or "approved" the design prior to build? Probably not. It is likely that the courts will require all contrac- tors to meet the stated requirements. That is, aer all, what they signed up to deliver. Key takeaways for contractors It won't be possible to avoid every dispute, but there are several important points that contractors should take away from this case: • Understand exactly what you are agree- ing to deliver. If you are being asked to deliver to seemingly inconsistent or highly challenging requirements, it is better to address these upfront. • Be realistic about what you can deliver. If you promise to deliver projects to require- ments that you cannot meet – whether that's down to commercial or other pres- sures – then you must understand you are facing potential claims from the outset. • Insert limitation of liability clauses into your contracts. These can be an effec- tive way of mitigating prospective claims, even if you are unable to understand the scope of potential issues pre-contract. • Pre-empt future disputes. The prospect of future disputes ought to place a greater focus on the effective operation of change control, notice provision and other con- tractual mechanisms around accept- ance and waiver. This applies to both the customer and the contractor/service provider. • Practice proper record keeping. The pros- ecution and defence of claims depends primarily on two things: (1) the contrac- tual background and (2) the provable fac- tual history of the project. The party that can best evidence its side of the story will inevitably have a substantial advantage. Proper record-keeping and keen contract management are critical to this. Contractors are under a huge amount of pressure to deliver energy projects accurately and efficiently. So, they need to make sure they understand whether they are agreeing to meet general or specific requirements. And the more complex the project, such as an offshore windfarm, the more careful they need to be. Where they agree to meet speci- fied criteria, contractors need to ensure they can and do meet those criteria – even when they are working to international standards or to a design approved by the customer. The legal action in the case above began in November 2013, and went through two appeals before the final decision was reached this year. It couldn't be clearer that the costs of getting it wrong – both in terms of money and time – are tremendous. Richard Twomey, partner, DWF Big projects: builders beware A court ruling has set a precedent that contractors must meet specified criteria – even when working to international standards or to a design approved by the customer, says Richard Twomey. Turbines at the Robin Rigg windfarm

Articles in this issue

Archives of this issue

view archives of Utility Week - UTILITY Week 17th November 2017