| 3rd - 9th March | UtILItY WEEK
Operations & Assets
High viz
Building work has started at this
Barratt Homes development at St
Oswald's View in Methley, West
Yorkshire aer the installation of an
underground carlow tank to help
alleviate floods.
The 96 by 27.4m tank can hold
2.3 million litres of water and was
installed in seven weeks by Carlow
Concrete. It compares the rate of flow
of storm water from the developed site
to the original 'greenfield' condition.
Tank holds back
the floodwaters