Utility Week

UTILITY Week 7th October 2016

Utility Week - authoritative, impartial and essential reading for senior people within utilities, regulators and government

Issue link: https://fhpublishing.uberflip.com/i/735063

Contents of this Issue

Navigation

Page 24 of 35

UTILITY WEEK | 7TH - 13TH OCTOBER 2016 | 25 Operations & Assets Andy Mitchell, chief executive, Tideway Q&A Is the construction work due to start on schedule? Our four tunnelling machines are being designed at the moment. They take about a year from decision-to-go to deliver-on-site, and we expect the first tunnel boring machine to arrive in May next year. The next two will then arrive later in the summer, and as soon as we've got down to the bottom of the shas, we'll be lowering the machines down them. Have you taken any learnings from previous large infrastructure projects? Hell yes. The precursors on the tunnelling are the Lee Tunnel and Crossrail, but also the National Grid tunnels which were going on at the same time. The tunnelling per year that we've got to do is somewhere between a third and a half of the tunnelling per year that was going on a couple of years ago. The Thames Tideway Tunnel starts in Hammersmith at about 30 metres deep, and goes down to about 65 metres deep where it meets the Lee Tunnel. But the Lee Tunnel keeps going again, it is deeper than anything we have got to do. Crossrail, being closer to the ground and under all sorts of listed buildings, had a lot more challenges in terms of proximity to neighbours, utilities, tube lines, gas pipes, water pipes. They had a much harder job there than we've got because we're under the river. There aren't any man- made structures above us, which is some- thing Crossrail would have loved, and we are not weaving in and out of all the tube systems in London. There are only two pipes that go lower than us and they are Thames Water assets, but very quickly we're below anything else. Critics claim the tunnel is not needed because there are cheaper alternatives available. What would you say to them? If you do the maths and work it through logically, the argument isn't a valid one. One of the reasons that our tunnel is a metre bigger in diameter than the Crossrail tunnels is because it has a volume of 1.6 million cubic metres. And the scale of blue-green response or capability that would be needed to replicate what the tunnel will do is enormous. Philosophically, are there other ways of addressing the issues that we have? Yes. Practically? No. Do you have any concerns about funding for the tunnel aer Brexit? No. Our funding structure involves equity from our shareholders. We have a number of covenants and restrictions on how the financing works, and there is a requirement that at all times we respect the 70:30 bor- rowing to equity ratio. Our shareholders decided to put £1.3 billion of their own money in first. Then, by the time the lenders' money was being deployed, a significant number of the risks would have been addressed – which I think was a smart move. The market has shown that we're an attractive place to put money. The point that we make to shareholders or potential lenders is that when we've finished [construc- tion], what we end up owning is the dumbest asset that anyone could ever invest in – a series of shas and tun- nels built to last. And there isn't a question mark over maintenance costs, because effectively there aren't any. We've spoken to many potential investors, all of whom see that this is worth putting money into. It's a good investment and that is why we've borrowed as we have, and we don't see that changing. So no, I don't have any concerns at all. Are you confident the project will be completed on time and on budget? Definitely. The main contractors have submitted contract programmes that show an 18-month-earlier completion, but the stretch target is the whole two years. We've been pursuing that from the beginning. We mobilised on all of our sites early, and we've got clear views as to what we've got to do to achieve that earlier schedule. Chasing an earlier programme, we find it very dif- ficult to see how we'll overrun on time and, therefore, how we'll overrun on cost. We've got no intention of running over on either of those two. We're one year in, we've started early. We have found problems and had delays, but we've found the delays earlier, and have dealt with a number of delays that were potentially there, but we've dealt with them before we would even have started on the original schedule. We're confident in our schedule, we're confident in our ability to achieve that at least the 18 months early, we're still confident in the budget and the contingency. "We're confident in our schedule, we're confident in our ability to achieve that at least the 18 months early, we're still confident in the budget and the contingency."

Articles in this issue

Archives of this issue

view archives of Utility Week - UTILITY Week 7th October 2016