18
| 30TH SEPTEMBER - 6TH OCTOBER 2016 | UTILITY WEEK
Operations & Assets
High viz
Eight offshore wind technicians from
the Humber area have just started
work on the installation of wind
turbine foundations at DONG Energy's
Race Bank offshore windfarm.
Race Bank is located off the north
Norfolk coast and is being built out of
DONG Energy's construction base in
the Grimsby Fish Docks. The offshore
windfarm will consist of 91 wind
turbines in total, each 177m tall.
With the first of two offshore sub-
stations – which link each turbine to
the main export cables that transmit
Eight join Race