High viz
Construction of the first phase of the
200MW Borkum West II offshore wind-
farm, a development in the German
North Sea, has been completed. The
last of the 40 wind turbines, about
45km north of the island of Borkum,
was installed in June and the project is
now being commissioned.
Renewable energy consultancy
SgurrEnergy has been involved in the
project for about five years, and moni-
tored construction, reporting monthly
Phase one complete
Photo:
Trianel