Operations & Assets High viz If you can't go up, go under 22 | 31st January - 6th February 2014 | utILIty WeeK When Iberdrola USA subsidiary NYSEG needed to expand capacity at Big Tree, its 1940s-built substation in Buffalo, New York state, it found there wasn't enough room to install the two new 115kV capacitor banks where they needed to be, so Connecticut-based company Kerite was given the job of burying the banks underground and connecting the whole thing up with underground cables. Usually, underground transmission