Water & Wastewater Treatment

January 2014

Water & Wastewater Treatment Magazine

Issue link: https://fhpublishing.uberflip.com/i/235881

Contents of this Issue

Navigation

Page 13 of 39

PROJECT FOCUS The biggest risk for us was a section going into the sewer out of alignment. "However, design tolerance was built-in to enable slight adjustments to be made and calculations were carried out to determine heave induced by excavation. Everything worked perfectly." Grouting Temporary shelters and acoustic curtains were installed to minimise odour and noise Precision-welding in the tunnel was to standards usually associated with very high-pressure pipelines A temporary metal and rubber cage was created to support the Ham Sewer 14 Water & Wastewater Treatment January 2014 The space between the liner and the existing brick was grouted through pre-formed grout holes using cementitious grout, to ensure there were no voids and that the loads from the TBM works would be transferred onto the new structural lining. A 450mm lateral connection was reconnected with a 500kg, 20mm-thick reinforcing plate, site-welded to distribute the load. Stakeholder and environmental management was a key factor on the project. The site was therefore protected by Haki temporary shelters and Soundex Acoustic curtains to minimise odour and noise for local residents. Jon Hynes, utilities agent, DSJV, said, "To install 50t of 50m-long duplex stainless steel liner into a live sewer, 10m below ground, and 500mm above the Crossrail running tunnels sums up the complex nature of the task that faced DS JV and UKDN Waterflow nicely. "However, it belies the extent of the consultation, interface and design progression that all partners embarked on a full 18 months before the first liner sections arrived on site. "From conception, it was clear that numerous parties had a stake in this game; from residents to asset owners, from the project manager to various designers, and from consultants to contractors. "In addition, to keep us all on our toes, we had the Drive Z TBM launching from the Pudding Mill Lane portal, some 100m east of us. "In other words, no liner - no launch." The first TBM successfully passed the reinforced section in August 2013, without incident. The second TBM is due to pass in 2014. With no injuries and a 100% safety record, the UKDN team's work on this site will continue until 2015 when the shafts will be reinstated. Most recently the team has inserted a UV-cured GRP liner into the adjacent Wick Sewer to provide additional protection. As this 1.2m-diameter sewer is slightly smaller, and that bit further away from the tunnelling works, a GRP lining could be used. UKDN Waterflow teams continue to deliver agile and ground-breaking stabilisation programmes at Crossrail sites throughout London. nnn wwtonline.co.uk

Articles in this issue

Links on this page

Archives of this issue

view archives of Water & Wastewater Treatment - January 2014