Utility Week

UW January 2023 HR single pages

Utility Week - authoritative, impartial and essential reading for senior people within utilities, regulators and government

Issue link: https://fhpublishing.uberflip.com/i/1488380

Contents of this Issue

Navigation

Page 25 of 43

26 | JANUARY 2023 | UTILITY WEEK Water High Viz Groundbreaking progress More milestones were reached on London's "super sewer" project over the back end of last year as it heads towards completion in 2027. The Thames Tideway project was granted an extension of six months by Ofwat because of Covid-19 and lockdowns delaying work on the pro- ject. It is now due to be handed over to Thames Water to operate by the end of August 2027. In November, Tideway's Blackfriars team completed the pour of the shaˆ roof – the second largest on the project. The 200 cubic-metre-pour took 10 hours to complete and was the culmination of an extensive programme of works in the shaˆ . The base slab, 58 metres below, was poured at the end of March last year. In the ensuing 20 months, the team has completed the shaˆ second- ary lining and baŒ e walls, installed two vortex tubes and the heading beam. The team has now moved on to the roof upstands, which will accommodate the access covers. They will also complete phase two of the air treatment chamber, which sits on the shaˆ roof slab. Once complete, the team can pour the slab ready for paving. Elsewhere, the team at Victoria Embankment Foreshore has started works to remove its co" erdam – the third site on the Central section to do so. The co" erdam contains 284 piles, which were driven between 10 and 12 metres into the clay under the river. As this job progresses, the new granite-clad river wall will meet the river for the • rst time as the vacated lower work area inside the co" erdam – oods. The • rst 10 of nearly 100 precast concrete river wall panels have also been installed at King Edward Memorial Park in Wapping. These panels will form the permanent riverside cladding for the site, which will extend the park out into the Thames.

Articles in this issue

Archives of this issue

view archives of Utility Week - UW January 2023 HR single pages