Utility Week

Utility Week 5th October

Utility Week - authoritative, impartial and essential reading for senior people within utilities, regulators and government

Issue link: https://fhpublishing.uberflip.com/i/1035740

Contents of this Issue

Navigation

Page 17 of 31

18 | 5TH - 11TH OCTOBER 2018 | UTILITY WEEK High viz Two years aer the Hinkley Point C project started, more than 3,200 peo- ple are working at the Somerset site. The pre-stressing gallery – the struc- ture below the reactor unit – for reac- tor one is complete, as is an excavation that is 21 metres below sea level for the 54 metre-tall water pumping station, and 750 metres of underground con- crete galleries for cables and pipes. EDF says the project is on track for its next major milestone in 2019 – the completion of the 4,500-tonne con- crete platform on which the reactor buildings sit. Looking further ahead, four UK contractors have formed an alliance to work on mechanical and electrical services, and heating, ventilation and air conditioning at the site. They are Hinkley C 'on target to hit milestones' Operations & Assets High viz

Articles in this issue

Archives of this issue

view archives of Utility Week - Utility Week 5th October